Preparing an RC drilling program: owner-side checklist

Prepare reverse-circulation drilling scope, sites, contractor interfaces, sample records and daily reconciliation before mobilization.

Sourdough Exploration resource libraryUpdated Jump to checklist ↓

The short answer

RC program preparation should connect the geological objective to executable sites, a clear contractor scope and a controlled sample workflow. Before mobilization, agree who owns each decision and what records will demonstrate that the work was completed as intended. Metres drilled alone are not a complete measure of a useful program.

What belongs in the owner’s brief?

State the question each proposed hole is intended to test and provide the current target and collar information with coordinate references. Distinguish a proposed design from a final instruction. Identify who can authorize changes to location, orientation, depth or termination criteria, and how that authorization is recorded.

This guide addresses program coordination, not a drilling design prescription. The responsible geological and drilling specialists must decide whether reverse circulation is appropriate for the target, ground conditions and required sample quality. A magnetic anomaly alone is not enough to declare a drill target ready.

How should the contractor scope expose interfaces?

Document what the contractor and project owner each supply: site readiness, transport, consumables, support personnel, sample handling arrangements and reporting. Clarify how delays, scope changes and standby are communicated and recorded. Align the assumptions in the schedule with those in the commercial scope.

Ask the relevant specialists to review access, rig suitability and site conditions before mobilization. Do not allow a map symbol to stand in for a practical site review. Confirm that the planned activities and supporting footprint have been considered in the applicable permission process.

What needs to be ready for the samples?

Agree identifiers, interval recording, sample collection responsibilities, quality-control procedures, storage and dispatch with the geological team and laboratory as applicable. Prepare the record system before the first sample, including how missing, wet, contaminated or otherwise problematic material will be documented and reviewed.

Keep the sample identifier connected to the hole, interval and custody record. A spreadsheet with plausible sequential numbers is not enough if the physical containers and dispatch documents cannot be reconciled. Rehearse a small end-to-end handoff to expose ambiguities while they are still inexpensive to fix.

What should a daily report reconcile?

Separate production, technical observations, sample movement, safety or operational issues, and decisions. Track completed work against the current authorized plan, not an obsolete starting schedule. Record the reason for a material deviation and the person who approved it.

Compare contractor records with the owner’s records regularly. Resolve inconsistent hole identifiers, intervals, time categories or consumable entries promptly. This supports both technical interpretation and cost control without treating speed as the only objective.

What is the closeout package?

Reconcile final hole and collar records, sample inventories, dispatch/custody documents, daily reports, approved changes and commercial records. Identify missing items and residual issues rather than presenting an incomplete package as final. Keep observed results separate from proposed follow-up.

Sourdough’s existing RC service is consultation and field management: program planning, contractor scoping, logistics review, sample-flow oversight and reconciliation. This checklist does not claim ownership of a rig, a particular production rate or a guaranteed geological result.

Your planning checklist

  • Hole objectives and current design responsibilities clear.
  • Coordinate references and site/access readiness checked.
  • Contractor and owner supply boundaries documented.
  • Permissions and supporting footprint reviewed.
  • Sample identifiers and custody workflow rehearsed.
  • Daily reporting, change approval and closeout records agreed.

Sources & further reading

Use official guidance for current requirements. These references support the subject matter; they have not reviewed or endorsed this article.

  1. Government of Yukon — Determine the class of your quartz exploration program ↗
  2. Government of Yukon — Find maps and records for mining claims and tenure ↗

General educational guidance, not legal advice, a site-specific technical design or a complete safety procedure. Confirm current requirements and project conditions with the responsible authorities and specialists.